New York Clarifies “Emergency” and “Essential” Construction

Robinson+Cole Construction Law Zone
Contact

Following Governor Cuomo’s order and the Empire State Development (ESD) guidance on March 27, 2020, which provided that all “non-essential construction” except “emergency construction” must shut down, this week the Commissioner of the New York City Department of Buildings issued clarification about the terms “emergency” and “essential” construction (the “Bulletin”).

According to the DOB’s Bulletin, “emergency construction” is permitted to continue until further notice. This is in addition to roads, bridges and transit facility construction projects which are authorized to continue under the Governor’s Executive Orders and ESD Guidance as “emergency construction”.  Id.  Emergency construction which the ESD guidance previously defined as a “project necessary to protect health and safety of the occupants”, has now been clarified to include:  a) emergency work ordered by the DOB, b) restoration of essential services – heat, hot water, cold water, gas, electricity or other utility services and c) work necessary for corrective action that “severely affects life, health, safety, property, or significant number of persons.” Id. Emergency construction is further articulated by the Bulletin as construction “required to continue to the extent that it would be unsafe to allow work to remain undone” but may “continue only until it is safe to shut the site.” Id.

Pursuant to the Bulletin, affordable housing, which the Governor characterized as “essential construction”, is further now defined as:

construction work on public housing, or a private or multiple dwelling or real property that is a new building (NB) that is 100% vacant or is work on unoccupied public housing units for the designation as housing for specific populations (i.e., shelter set aside, domestic violence referrals), or work on the exterior to address emergency conditions requiring immediate corrective action, set forth in Section 1(a)(iii) or within public housing, correction of critical systems for seasonal preparedness for the 2020-2021 heating season of an existing public housing building. Construction work on a private or multiple dwelling or real property that is a new building (NB) or that is 100% vacant that is now used or will be converted to such use: (i) For the provision of affordable inclusionary housing or mandatory inclusionary housing pursuant to the New York city zoning resolution; or (ii) Where no less than 30% of the residential units are subject to a regulatory agreement, restrictive declaration, or similar instrument with a local, state, or federal governmental entity or a local housing authority in a city with a population of one million or more.

Information about New York City’s Inclusionary Housing Program, including maps, is accessible here.

The information provided is current as of April 3, 2020, however, since this area remains somewhat fluid, checking for updates is recommended.

[View source.]

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Robinson+Cole Construction Law Zone | Attorney Advertising

Written by:

Robinson+Cole Construction Law Zone
Contact
more
less

Robinson+Cole Construction Law Zone on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide